Weekly Update: August 9, 2018

August 9, 2018

Check out August 9th’s Kingfish Bay Construction Updates.

Caribbean pastels, lush tropical landscaping, Bahama shutters … and surrounded by the beauty of the Carolina coast. Truly breathtaking!

  • Painted the exterior of B-17 Angelfish
  • Installed carpet in the guest bedroom of CV-7 Tarpon
  • Landscaping is complete in the front yards of CV-7 and CV-9 Tarpons
  • Hot tubs, pavers and landscaping have been installed in the courtyard’s of CV-7 &  CV-9 Tarpon
  • Fencing has been installed for CV-7, CV-9 (tarpons) and CV-10 Marlin
  • Installed Bahama shutters for CV-4 Marlin
  • Plumbing fixtures have been installed in CV-10 Marlin
  • The shower has been tiled in CV-10 Marlin
  • Bahama shutters have been installed in CV-10 Marlin
  • Carpet and handrails have been installed in CV-10 Marlin
  • Hot tub, pavers and landscaping have been installed in the courtyard of CV-10 Marlin
  • Delivered sod for C-9 Bonita
  • Installed carpet and handrails in C-9 Bonita
  • Installed the shower door in C-7 Albacore II
  • Installed carpet and handrails in C-7 Albacore II
  • Starting to lay sod for C-7 Albacore II
  • Starting to plant palm trees by B-1 Seahorse