Weekly Update: March 19, 2019

March 26, 2019

Check out March 19th’s Kingfish Bay Construction Updates.

More sticks going up!

  • First coat of interior paint has been applied and interior trim installed C-15 Anchor Coral
  • Starting to paint the final coat of interior paint C-17 Albacore
  • Appliances have been installed in Albacore II
  • Driveway slab poured for C-18 Albacore II
  • Slab has been poured and starting to frame C-14 Albacore II
  • Framing and sheathing CV-15 Tarpon
  • Framing, sheathing and beginning to install house wrap on CV-20 Longfin