August 2, 2018Check out August 2nd’s Kingfish Bay Construction Updates.
Nice!
- Appliances have arrived for B-14 Angelfish
- Working on trim work in B-17 Angelfish
- Installed new interior lighting in CV-4 Marlin
- Installed ceramic and deco tile in C-9 Bonita
- Starting to install fencing around CV-7 Tarpon
- Planted shrubbery for CV-7 Tarpon
- Finished installing CoreTec Flooring in CV-7 Tarpon
- Installed mirrors and plumbing fixtures in C-7 Albacore II
- Paint touch-ups are complete in B-1 Seahorse
- Plants have been delivered to add to the landscaping throughout