April 9, 2019Check out April 2nd’s Kingfish Bay Construction Updates.
At Kingfish Bay, the breathtaking views and natural setting is just the beginning of the journey.
- Installed flooring C-15 Anchor Coral
- Tile installed C-15 Anchor Coral
- Installed cabinets and set appliances C-5 Cobia
- Countertops have been installed C-5 Cobia
- Flooring has been installed C-5 Cobia
- Frame detail for the fireplace C-5 Cobia
- Driveway poured for C-17 Albacore
- Rough HVAC C-14 Albacore II
- Shutters installed on C-18 Albacore II
- House wrapped CV-15 Tarpon
- Rough plumbing CV-20 Longfin
- Foundation is prepped and ready for slab to be poured B-20 Seahorse