Weekly Update: August 20, 2019
August 20, 2019Check out August 20th’s Kingfish Bay Construction Updates.
There’s still room for you in paradise.
- Shower door C-55 Albacore II
- Mirror and bathroom accessories C-55 Albacore II
- Drywall CV-8 Longfin
- Shiplap accent wall installed CV-18 Longfin
- Tower accent installed CV-18 Longfin
- Foundation framed and under slab plumbing CV-17 Tarpon
- Backsplash in kitchen of C-41 Anchor Coral II
- Caulking the exterior of B-25 Angelfish
- Framed out the pool for C-32 Parrotfish II
- Sheathing installed on SF-27 Amberjack