Weekly Update: March 12, 2020
March 12, 2020Check out March 12th’s Kingfish Bay Construction Updates.
- HVAC trim C-42 Albacore II
- Painting exterior CV-16 Longfin
- Poured slab on C-25 Anchor Coral II
- Framing and wrapping house on B-24 Angelfish
- Framing B-30 Seahorse
- Mudded drywall B-34 Seahorse
- Poured driveway and walkway SF-26 Blue Dawn
- Riverfront Park Progress