Check out May 28th’s Kingfish Bay Construction Updates.
- Cabinets installed C-42 Albacore II
- Exterior Lighting C-42 Albacore II
- Drywall mudded C-49 Albacore II
- Painting Exterior CV-19 Longfin Elevation II
- Railing on upper level Veranda B-24 Angelfish
- Plumbing fixtures SF-31 Sea Star
- Laundry cabinets SF-31 Sea Star
- Final plumbing trim SF-31 Sea Star
- Pier progress