Weekly Update: July 6, 2021
August 10, 2021We’re putting out the “Welcome Home” mat. Ready to come home to Kingfish Bay, yet?
Check out July 6th’s Kingfish Bay Construction Updates.
- Graded lot B-35 Seahorse
- Exterior paint B-36 Seahorse
- Slab poured C-24 Albacore II
- Under slab plumbing CV-21 Marlin
- Rough electric trim C-22 Mako
- Boxed foundation SF-18 Alpinia
- Boxed foundation SF-28 Bluefin
- Pool SF-37 Amberjack II
- Bathroom floor tile SF-37 Amberjack II
- Flooring SF-37 Amberjack II
- Laundry room tile SF-37 Amberjack II