B-14 Angelfish
- Carpet has been installed
- Plumbing fixtures have been installed
- Ceramic tile in the shower has been installed
- Countertops, cabinets and backsplash have been installed
B-17 Angelfish
- Started to paint the exterior
- Installed sheetrock
CV-3 Marlin
- Completed the landscaping
- Set appliances
- Installed pavers in the back courtyard area
CV-10 Marlin
- Installed ceramic tile in the shower
- Installed flooring finishes
- Installed cabinets, countertops, and backsplash
- Installed pavers and adding sod in the backyard
- Completed the landscaping in the front
CV-7 Tarpon
- Installed countertops, cabinets and backsplash
- Starting to install the flooring finishes
- Installed pavers in the courtyard area
- Preparing to add plants to the landscape in the front and back
CV-9 Tarpon
- Installed ceramic tile in the shower
- Installed plumbing fixtures
- Installed cabinets, countertops, and backsplash
- Installed floor finishes
- Installed pavers in the backyard
C-7 Albacore II
- Installed interior lighting fixtures
- Completed the design of the fireplace
- Installed the flooring finishes
- Completing trim work
- Installed cabinets and countertops
B-1 Seahorse
- Cabinets, countertops and backsplash has been installed
- Plumbing fixtures have been installed
- Tile has been installed in the shower
- Floor finishes have been installed
https://youtu.be/_x7Fiz1GoAM