Bath House Updates and More!
December 1, 2017- Countertops have been installed in the Bath House
- The benches are getting framed in the Bath House
- Hand rails and shower plumbing accessories have been installed in the Bath House
- Partitions and paper towel dispenser have also been installed in the Bath House
- The Spa Pavilion is under roof and sheathing is almost done
- The front of the Marlin on CV-4 has shingles and they are working on the roof at the back of the house
- Angelfish on B – 13 is in the final stages of framing
- The crew is in the final stages of siding installation on the Tarpon on CV-9
- The Marlin on CV-10 is getting prepped for roofing
- C-11 Cobia is getting touch up paint
- Drywall is going in C-10 Albacore
- Albacore on C-8 has insulation
- The interior is getting prepped and painted on C-2 Albacore
- Fencing around the pool courtyard has been installed at the Cobia on C-1