Check out April 2nd’s Kingfish Bay Construction Updates.

At Kingfish Bay, the breathtaking views and natural setting is just the beginning of the journey. 

  • Installed flooring C-15 Anchor Coral
  • Tile installed C-15 Anchor Coral
  • Installed cabinets and set appliances C-5 Cobia
  • Countertops have been installed C-5 Cobia
  • Flooring has been installed C-5 Cobia
  • Frame detail for the fireplace C-5 Cobia
  • Driveway poured for C-17 Albacore
  • Rough HVAC C-14 Albacore II
  • Shutters installed on C-18 Albacore II
  • House wrapped CV-15 Tarpon
  • Rough plumbing CV-20 Longfin
  • Foundation is prepped and ready for slab to be poured B-20 Seahorse