Weekly Update: April 26, 2018
April 26, 2018Check out April 26th’s Kingfish Bay Construction Updates!
Come Live Relaxed … in this private slice of paradise!
- Rough mechanical, electrical, plumbing is installed for B-11 Angelfish
- Final electric is complete and power is on B-13 Angelfish
- First coat of interior paint is complete for B-14 Angelfish
- Sod and landscaping has been added to the front of CV-5 Tarpon
- A fence is being installed between CV-4 Marlin and CV-5 Tarpon
- Installing the grinder pump for CV-1 Tarpon
- Final electric is complete and power is on CV-9 Tarpon, B-13 Angelfish, CV-1 Tarpon, and CV-10 Marlin
- Landscaping has been added to CV-4 Marlin
- Front door of CV-10 Marlin has been painted
- Installing the tile in the master bathroom of CV-3 Marlin
- The pool has been plastered in C-11 Cobia
- Painting the interior of C-9 Bonita
- Siding is completely installed and the flashing in on C-4 Albacore II
- Slab has been poured for B-1 Seahorse