August 29, 2019Check out August 29th’s Kingfish Bay Construction Updates.
Kingfish Bay … where Living Relaxed is a way of life.
- Starting to prime interior or CV-8 Longfin
- Accent at knee wall CV-18 Longfin
- Cabinets are being installed CV-18 Longfin
- Slab poured CV-17 Tarpon
- Interior painting completed B-25 Angelfish
- Rough plumbing B-31 Seahorse
- Rough HVAC B-31 Seahorse
- Rough HVAC trim SF-27 Amberjack