Weekly Update: February 6, 2020

February 6, 2020

Check out February 6th’s Kingfish Bay Construction Updates.

Not sure if you heard the news but groundhog Punxsutawney Phil says spring is on the way!

  • Painted interior C-21 Albacore II
  • Pool CV-8 Longfin
  • Framing CV-16 Longfin
  • Pool CV-17 Tarpon
  • Starting to frame B-34 Seahorse
  • Retaining wall C-43 Hawkfish
  • Framed interior stairs SF-31 Sea Star
  • Rough Electric trim SF-31 Sea Star
  • Rough HVAC trim out complete SF-31 Sea Star