Weekly Update: January 25, 2018
Check out January 25th’s Kingfish Bay Construction Updates!
Things are rapidly progressing in “The Carolina’s Newest Coastal Community.”
1. Exterior lighting has been added to Albacore’s C-2 and C-8
2. Starting construction on the pool for C-2 Albacore
3. Framing & Sheathing the 2nd Story of Angelfish B-12
4. Painting is still in progress for the exterior of CV-5 Tarpon
5. Final HVAC install for C-11 Cobia
6. Working on underground electric around the Courtyard Villas
7. Construction on Sunset Beach Clubhouse
• Elevator Shaft
• Footers for the front entrance
• Water lines going into the building
• Sewer lines coming out