Off and running, in the New Year!
- Added plants to the front landscape of CV-6 Longfin
- Installing pavers around the pool area of CV-6 Longfin
- C-5 Cobia is under roof
- Exterior painted for B-5 Sand Dollar
- Painting the interior of B-5 Sand Dollar
- Electrical, HVAC, and Plumbing trim out complete for B-32 Seahorse
- Framing and sheathing C-17 Albacore
- HVAC and Plumbing trim out complete for C-18 Albacore II