Weekly Update: July 11, 2019
July 11, 2019Check out July 11th’s Kingfish Bay Construction Updates.
ALL ABOARD THE KINGFISH BAY TROLLEY! Next stop, the Kingfish Bay Oceanfront Clubhouse at Sunset Beach!
- Pavers installed C-14 Albacore II
- Final plumbing trim, hardware, and accessories installed C-14 Albacore II
- Appliances installed C-14 Albacore II
- Tile installed C-55 Albacore II
- Stairs, handrail and trim installed C-55 Albacore II
- Framing CV-8 Longfin
- Painting exterior trim CV-14 Longfin
- Starting to install siding CV-18 Longfin
- C-13 Anchor Coral II house wrapped
- Underground electric installation C-32 Parrotfish II