Latest News
Weekly Update: July 30, 2019
July 30, 2019Check out July 30th’s Kingfish Bay Construction Updates.
Kingfish Bay, offering an extraordinary lifestyle.
- HVAC trim for B-25 Angelfish
- House wrapped B-31 Seahorse
- Sliding doors installed C-13 Anchor Coral II
- Driveway and walkway framed for concrete C-32 Parrotfish II
- Siding installation CV-8 Longfin
- Interior painted CV-14 Longfin
- Insulation CV-18 Longfin
- Prepping foundation for slab SF-27 Amberjack