Lookin’ good!
- Flooring has been installed in B-13 Angelfish
- Plumbing fixtures are set in B-13 Angelfish
- Appliances and countertops are in B-13 Angelfish
- Mantel has been built and installed in B-11 Angelfish for the fireplace
- Flooring is installed in B-11 Angelfish
- Countertops are installed in B-11 Angelfish
- Starting to frame and sheath the second floor of Angelfish B-17
- Painting the interior of C-4 Albacore II
- Starting to install the light fixtures in C-4 Albacore II
- Installed insulation in C-7 Albacore II
- Installing the siding on B-1 Seahorse