SPRING SAVINGS: $15,000 to Use as You Choose* on available inventory or home plan! Offer expires 4/30.
Contact us today or click here to learn more!

Latest News

Weekly Update: June 19, 2018

June 19, 2018

Check out June 19th’s Kingfish Bay Construction Updates.

Ready to move in?

  • Fireplace is in B-11 Angelfish and ready to have the stone installed
  • Installed roof trusses on B-17 Angelfish
  • Installed countertops in the kitchen and bathroom in C-3 Bonita
  • Installed shower door in C-3 Bonita
  • In the process of staining the steps in C-3 Bonita
  • Installing the backsplash in C-4 Albacore II
  • Planting trees/bushes for the landscape C-4 Albacore II
  • The cement shake has been painted on B-1 Seahorse
  • Drywall has been installed in B-1 Seahorse