Weekly Update: June 26, 2018

June 27, 2018

Check out June 26th’s Kingfish Bay Construction Updates.

Come enjoy the “kick back” Caribbean vibe of Kingfish Bay.

  • Completely installed Cabinets in B-14 Angelfish
  • Framed shower seat in B-14 Angelfish
  • Installed lighting fixtures in B-11 Angelfish
  • Starting to layout plants for the landscape around B-11 Angelfish
  • Screened in the top porch of B-11 Angelfish
  • Painted the exterior of B-11 Angelfish
  • Set windows in B-17 Angelfish
  • Cabinets are installed in CV-10 Marlin
  • Finished tile work in CV-4 Marlin
  • Painted the exterior of B-1 Seahorse
  • Finished the drywall in B-1 Seahorse
  • Framed the foundation for CV-6 Longfin