The beauty of nature surrounds!
- Placed sod around Angelfish B-12, B-13, and B-14
- Installing shutters or Angelfish B-14, B-13, and B-11
- Painted exterior of Angelfish B-11
- Prepping for tile installation in bathroom of Angelfish B-11
- Applied first coat of interior paint for Angelfish B-11
- Installed cabinets in B-13 Angelfish
- Adding sod and landscaping around C-3 Bonita
- Installed appliances and backsplash in the kitchen of CV-1 Tarpon
- Starting to lay sod by CV-4 Marlin
- The flooring is being installed in C-4 Albacore II
- Installed shiplap accent walls in the living room and master bedroom of C-4 Albacore II
- Fencing installed around C-4 Albacore II
- Tiled bathroom of C-4 Albacore II
- Installing the siding on C-7 Albacore II
- Finished installing the roof on B-1 Seahorse
- Finishing up the construction of the Nature Pavilion
- Added picnic benches, walkways and working on Bocce Ball and corn hole areas in the picnic area
- Putting green by the Clubhouse is almost complete
- Created a walkway by the putting green and nature pavilion