Weekly Update: March 15, 2018
March 15, 2018Check out March 15th’s Kingfish Bay Construction Updates! We’re sprouting and blooming!
- Landscaping added around the Clubhouse and model homes
- Both Marlin Exteriors (CV-10 & CV-3) have been painted
- Concrete has been poured for entrance/walkways for CV-4 Marlin, CV-5 Tarpon, and B-15 Angelfish
- Setting roof trusses for C-4
- C-2 Albacore is complete and has been sold/closed (exterior and kitchen pic attached)
- Lighting fixtures are in C-10 Albacore
- The bathrooms are tiled in C-10 Albacore