MARCH MADNESS: $10,000 towards upgrades, closing costs or prepaids* on select move-in ready inventory! Offer expires 3/31.
Contact us today or click here to learn more!

Latest News

Weekly Update: March 19, 2019

March 26, 2019

Check out March 19th’s Kingfish Bay Construction Updates.

More sticks going up!

  • First coat of interior paint has been applied and interior trim installed C-15 Anchor Coral
  • Starting to paint the final coat of interior paint C-17 Albacore
  • Appliances have been installed in Albacore II
  • Driveway slab poured for C-18 Albacore II
  • Slab has been poured and starting to frame C-14 Albacore II
  • Framing and sheathing CV-15 Tarpon
  • Framing, sheathing and beginning to install house wrap on CV-20 Longfin

https://youtu.be/36MwWijmKuw