Latest News
![](https://kingfishbaydevelopment.com/wp-content/uploads/2019/03/cv-15-2-1280x1206.jpg)
Weekly Update: March 19, 2019
March 26, 2019Check out March 19th’s Kingfish Bay Construction Updates.
More sticks going up!
- First coat of interior paint has been applied and interior trim installed C-15 Anchor Coral
- Starting to paint the final coat of interior paint C-17 Albacore
- Appliances have been installed in Albacore II
- Driveway slab poured for C-18 Albacore II
- Slab has been poured and starting to frame C-14 Albacore II
- Framing and sheathing CV-15 Tarpon
- Framing, sheathing and beginning to install house wrap on CV-20 Longfin