YEAR-END KEYS EVENT: Exclusive Move-In-Ready Packages or Receive Up To $15,000* on selective inventory and homesites! Offer expires 12/31/25.
Call today or click to learn more!

Weekly Update: March 19, 2019

March 26, 2019

Check out March 19th’s Kingfish Bay Construction Updates.

More sticks going up!

  • First coat of interior paint has been applied and interior trim installed C-15 Anchor Coral
  • Starting to paint the final coat of interior paint C-17 Albacore
  • Appliances have been installed in Albacore II
  • Driveway slab poured for C-18 Albacore II
  • Slab has been poured and starting to frame C-14 Albacore II
  • Framing and sheathing CV-15 Tarpon
  • Framing, sheathing and beginning to install house wrap on CV-20 Longfin

https://youtu.be/36MwWijmKuw

Move-In Ready Inventory