March 22, 2018Check out March 22nd’s Kingfish Bay Construction Updates!
Some “Finishing Up” and beautiful “New Beginnings” at Kingfish Bay!
- Pool is formed for C-3 Bonita
- Drywall has been installed in C-3 Bonita
- C-4 Albacore II is under roof
- Drywall has been installed in C-6 Albacore
- Tile is installed in the bathrooms of C-10 Albacore
- Landscaping around C-10 Albacore and C-11 Cobia
- Interior and exterior lighting fixtures have been installed in CV-3 Marlin