Latest News

Weekly Update: March 29, 2018

March 29, 2018

Check out March 29th’s Kingfish Bay Construction Updates!

Get ready to Live Relaxed.

  • Starting to frame B-11 Angelfish
  • Installing drywall in B-12 Angelfish
  • Painting the exterior of CV-7 Tarpon
  • Painting exterior of CV-9 Tarpon
  • The pool is completely framed for CV-5 Tarpon
  • First coat of interior paint is complete for CV-1 Tarpon
  • Appliances are installed in C-11 Cobia
  • Installing insulation in C-9 Bonita
  • They are in the process of installing the floors in C-10 Albacore
  • Slab was poured for C-7 Albacore II
  • Framing is complete for C-4 Albacore II
  • Adding landscape and sod around Seahorse B -16
  • Sidewalks have been poured around the bungalow area

 