Check out November 26th’s Kingfish Bay Construction Updates.

Wishing you all a Happy Thanksgiving!

  • Starting siding installation C-12 Albacore II
  • Framing C-21 Albacore II
  • Painted exterior C-40 Albacore II
  • Framing C-38 Anchor Coral II
  • Painting exterior of B-22 Angelfish
  • Prepping for the slab on B-23 Angelfish
  • Painted exterior of B-28 Angelfish
  • Siding installed on B-29 Seahorse
  • Landscaping B-31 Seahorse
  • Roofing going on C-43 Hawkfish
  • Prepped and ready for slab SF-26 Blue Dawn
  • Completed the stucco accent at the entrance on SF-27 Amberjack
  • Landscaping the second island on Tilapia Way