Check out October 31st’s Kingfish Bay Construction Updates.

It’s spooky how AMAZING this community is becoming, HAPPY HALLOWEEN!

  • Framing C-12 Albacore II
  • Foundation framed C-21 Albacore II
  • Wrapping house C-40 Albacore II
  • Installing roof felt B-22 Angelfish
  • Siding B-28 Angelfish
  • Drywall B-2 Seahorse
  • Framing B-29 Seahorse
  • Drywall C-23 Parrot Fish II
  • Shower door installed SF-27 Amberjack
  • Countertops installed SF-27 Amberjack
  • Framing C-43 Hawkfish
  • Foundation framed SF-26 Blue Dawn