Kingfish Bay … a look on the bright side.

Check out October 6th’s Kingfish Bay Construction Updates.

  • Drywall C-20 Albacore
  • Drywall C-36 Albacore
  • Flooring B-18 Seahorse
  • Mudding drywall C-54 Bonita
  • Roofing C-39 Mako
  • HVAC trim C-19 Parrotfish II
  • Front door painted SF-25 Bluefin
  • Laundry room accent wall SF-25 Bluefin
  • Kitchen SF-25 Bluefin
  • Painted living room SF-25 Bluefin
  • Master bathroom SF-25 Bluefin
  • Pool SF-25 Bluefin
  • Painted shutters SF-25 Bluefin
  • Exterior light fixture B-4 Sand Dollar

https://youtu.be/T9-E9E2tpWk