September 10, 2020Check out September 10th’s Kingfish Bay Construction Updates.
- Rough electric trim C-20 Albacore
- Exterior doors C-36 Albacore
- Painted fence C-25 Anchor Coral II
- Sod C-25 Anchor Coral II
- Interior doors and trim B-18 Seahorse
- Starting to prep for roofing C-54 Bonita
- Framing C-39 Mako
- Starting to frame C-19 Parrotfish II
- Parrotfish II C-23 Front Elevation
- Parrotfish II C-23 Pool
- Plumbing for pool SF-25 Bluefin
- Bluefin SF-25 Front Elevation
- Bluefin SF-25 Pool Progress
- Blue Dawn SF-26 Front Elevation
- Blue Dawn SF-26 Pool Progress