Weekly Update: February 26, 2019
March 7, 2019Check out February 26th’s Kingfish Bay Construction Updates.
Fourteen models to choose from! Which one will be yours?
- Starting to work on the landscaping for B-32 Seahorse
- Poured the sidewalk for B-32 Seahorse
- Starting to install tile in the bathroom and shower of C-5 Cobia
- Mudding the drywall for C-15 Anchor Coral
- Painted the exterior of C-17 Albacore
- Laying the floor in C-18 Albacore II
- Framed the foundation for CV-15 and CV-20 in Phase 2A