Weekly Update: February 6, 2018
February 6, 2018Check out February 6th’s Kingfish Bay Construction Updates! Beautiful things are happening at “The Carolina’s Newest Coastal Community.”
- House wrap is on and windows are installed B-12 Angelfish
- Exterior painting and trim is complete on CV-5 Tarpon
- Flooring in the great room and kitchen has been installed C-11 Cobia
- Plumbing fixtures in the kitchen of C-11 Cobia
- Exterior lighting on C-10 Albacore
- Shower has been tiled in C-8 Albacore
- Interior light fixtures C-8 Albacore
- Siding is almost completely installed on C-6 Albacore