Weekly Update: January 30, 2020
January 30, 2020Check out January 30th’s Kingfish Bay Construction Updates.
Enjoy a relaxed lifestyle snuggled within a scenic hardwood forest, wetlands, and coastal bluffs.
- Graded lot C-42 Albacore II
- Slab poured CV-16 Longfin
- Drywall B-23 Angelfish
- Slab poured on B-34 Seahorse
- Painting interior doors SF-26 Blue Dawn
- Priming interior SF-26 Blue Dawn
- Bath hardware and accessories C-23 Parrotfish II
- Tile installed C-43 Hawkfish
- Flooring installed C-43 Hawkfish
- Trimming exterior for siding installation SF-31 Sea Star