Check out July 10th’s Kingfish Bay Construction Updates.

More Caribbean-style style homes going up! Homes built to stand up to the elements … while looking incredible!

  • Starting to install siding on B-17 Angelfish
  • Installed the shingles and metal ribbed roofing accents for B-17 Angelfish
  • Preparing to install concrete pavers and spa for the enhanced landscaping package for CV-10 Marlin
  • Installed cabinets in CV-10 Marlin and CV-9 Tarpon
  • Painting interior of C-7 Albacore II
  • Added trim accent around the fireplace in C-7 Albacore II
  • Finished installing the shiplap accent walls in the master and guest bedroom in C-7 Albacore II
  • Installed the tile in the shower of C-7 Albacore II
  • Poured slab for CV-6 Longfin
  • Laying sod and landscape around the Bungalow section

 