Latest News
Weekly Update: July 23, 2019
July 23, 2019Check out July 23rd’s Kingfish Bay Construction Updates.
Beautiful scenery, luxurious homes, and relaxed living … all waiting for you at Kingfish Bay!
- Bathroom tiled CV-14 Longfin
- Exterior is getting painted on CV-18 Longfin (2 pics)
- Landscaping added to CV-20 Longfin
- Roofing installed C-13 Anchor Coral II
- Windows and door set on C-13 Anchor Coral II
- Garage door installed C-41 Anchor Coral II
- House wrapped and windows set on B-25 Angelfish
- Slab ready for framing B-31 Seahorse
- Backsplash installed in kitchen of CV-15 Tarpon
- Front door painted CV-15 Tarpon
- Framed foundation and completing under slab plumbing SF-27 Amberjack